Warranty Information

Refer to the GE Lighting Solutions website for warranty information.

Power Supply Installation

  1. Connect the AC line to the black (line) and white (neutral) input wires of the power supply using 18-14 AWG (0.82-2.08 mm²) or 18-10 AWG (0.82-5.26 mm²) twist-on wire connectors.
  2. Connect the supply wire that is attached to the Tetra LED System to the red (+) and black (-) output wires of the power supply as outlined in the "Electrical Connections" section of your LED system's Installation Instructions.

NOTE: Power Supply Loads

Exceeding maximum load will cause the power supply to shut down. Once the excess load is removed, cycle the input power to restart the power supply.

Specific load information for the supported LED systems can be found in the "Power Supply Specifications" section on the next page.

NOTE: For CSA approval

a disconnect/toggle switch of appropriate rating needs to be placed within 29 feet (8.84 meters) of primary side of the power supply. The minimum rating of the switch must be either 120 or 220 Volts AC. The switch must also support twice the amount of input current.